Form TP-03 · Time Schedule, Milestones & Payment Schedule

Time Schedule, Milestones and Payment Schedule

A bar chart the evaluator can read in ten seconds, plus the payment ladder that has to match it. If the percentages here do not match the BOQ sections, the offer is internally inconsistent.

Contract period12 months
Zones3
Milestones6
Rev.A
Consistency test: the value of work complete at each milestone must equal the cumulative payment percentage claimed at that milestone, and both must be defensible from the BOQ. Three documents — programme, payment schedule and BOQ summary — are read together by every competent evaluator.

1 Schedule Particulars

2 Bar Chart (Gantt)

ActivityM1M2M3M4M5M6M7M8M9M10M11M12
Mobilisation & site establishmentTemporary facilities, survey, HSE set-up
Setting-out & excavationFoundations, tie beams, dewatering
Blinding & substructure concreteFootings, tie beams, backfill
Superstructure — frameColumns, beams, slabs, 7-day cycle
Blockwork & internal wallsFollows structure two floors behind
MEP first fixContainment, sleeves, pipework in slabs
Envelope & waterproofingRoof, external walls, wet areas
MEP second fixCable, pipework, ductwork, terminals
Plaster & screedWet trades complete before finishes
Tiling, painting & joineryMock-up release per finish type
External works & landscapingPaving, drainage tie-in, kerbs
Testing & commissioningTAB, fire alarm, electrical, integrated test
Snagging & handoverPunch list, O&M, training, keys
Defects liability period12 months from substantial completion
Bar chart is indicative of sequence and overlap; the contract programme issued after award is a critical-path network with resource loading.

3 Planned Monthly Progress

MonthM1M2M3M4M5M6M7M8M9M10M11M12Total
Planned cumulative %411193042536374859398100100
Planned value (USD)

Fill the planned value row from the BOQ summary so that the cash curve, the programme and the payment schedule are three views of one plan.

4 Milestones and Payment Schedule

#MilestoneCompletion criterionCum. %Payment %Retention %
1Mobilisation completeSite facilities operational, HSE plan approved, survey transferred4%4%10%
2Substructure completeAll footings and tie beams cast, backfill tested and approved19%15%10%
3Superstructure completeRoof slab cast, structure signed off by the structural engineer53%34%10%
4Envelope & first fix completeBuilding weathertight, MEP first fix tested in sections74%21%10%
5Substantial completionFinishes complete, commissioning reports issued, CO applied for93%19%10%
6HandoverAs-builts, O&M, warranties, training and keys delivered100%7%10%

Retention and release

Retention is deducted at the stated rate from each interim payment until the cap stated in the contract is reached. Half is released on the certificate of substantial completion; the balance on the certificate of completion of the defects liability period, against the maintenance certificate.

5 Schedule Control

Planning engineer
Project manager
Contracts manager