A bar chart the evaluator can read in ten seconds, plus the payment ladder that has to match it. If the percentages here do not match the BOQ sections, the offer is internally inconsistent.
| Activity | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | M10 | M11 | M12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Mobilisation & site establishmentTemporary facilities, survey, HSE set-up | ||||||||||||
| Setting-out & excavationFoundations, tie beams, dewatering | ||||||||||||
| Blinding & substructure concreteFootings, tie beams, backfill | ||||||||||||
| Superstructure — frameColumns, beams, slabs, 7-day cycle | ||||||||||||
| Blockwork & internal wallsFollows structure two floors behind | ||||||||||||
| MEP first fixContainment, sleeves, pipework in slabs | ||||||||||||
| Envelope & waterproofingRoof, external walls, wet areas | ||||||||||||
| MEP second fixCable, pipework, ductwork, terminals | ||||||||||||
| Plaster & screedWet trades complete before finishes | ||||||||||||
| Tiling, painting & joineryMock-up release per finish type | ||||||||||||
| External works & landscapingPaving, drainage tie-in, kerbs | ||||||||||||
| Testing & commissioningTAB, fire alarm, electrical, integrated test | ||||||||||||
| Snagging & handoverPunch list, O&M, training, keys | ||||||||||||
| Defects liability period12 months from substantial completion |
| Month | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | M10 | M11 | M12 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Planned cumulative % | 4 | 11 | 19 | 30 | 42 | 53 | 63 | 74 | 85 | 93 | 98 | 100 | 100 |
| Planned value (USD) |
Fill the planned value row from the BOQ summary so that the cash curve, the programme and the payment schedule are three views of one plan.
| # | Milestone | Completion criterion | Cum. % | Payment % | Retention % |
|---|---|---|---|---|---|
| 1 | Mobilisation complete | Site facilities operational, HSE plan approved, survey transferred | 4% | 4% | 10% |
| 2 | Substructure complete | All footings and tie beams cast, backfill tested and approved | 19% | 15% | 10% |
| 3 | Superstructure complete | Roof slab cast, structure signed off by the structural engineer | 53% | 34% | 10% |
| 4 | Envelope & first fix complete | Building weathertight, MEP first fix tested in sections | 74% | 21% | 10% |
| 5 | Substantial completion | Finishes complete, commissioning reports issued, CO applied for | 93% | 19% | 10% |
| 6 | Handover | As-builts, O&M, warranties, training and keys delivered | 100% | 7% | 10% |
Retention is deducted at the stated rate from each interim payment until the cap stated in the contract is reached. Half is released on the certificate of substantial completion; the balance on the certificate of completion of the defects liability period, against the maintenance certificate.