Who owns quality, which inspections are hold points, what happens when work fails, and how records prove it afterwards.
We deliver the Works to the specification, first time, and we prove it with records. The quality system on this project is a project-specific plan subordinate to our certified quality management system and is auditable against it. Conformance is verified by inspection and test before work is covered, not by retrospective argument after it is rejected.
| # | Objective | Target | Verification |
|---|---|---|---|
| 1 | First-time acceptance of structural inspections | ≥ 95% | Inspection register |
| 2 | Non-conformances closed within 14 days | 100% | NCR log |
| 3 | Concrete cube results meeting the specified class | ≥ 97.5% at 28 days | Cube test register |
| 4 | Services pressure tests passed first attempt | ≥ 90% | Test sheets |
| 5 | Snags per unit at handover | ≤ 3 | Snag list |
| 6 | Document transmittals acknowledged within 3 working days | 100% | Transmittal log |
| Role | Quality responsibility | Authority |
|---|---|---|
| Project Manager | Owns the QA/QC plan, chairs the weekly quality meeting, approves NCR disposition | Stops work on any non-conforming activity |
| QA/QC Engineer | Issues inspection requests, witnesses hold points, maintains registers, raises NCRs | Rejects work; may not be overruled by production |
| Site Engineer | Raises inspection requests ahead of covering work, maintains as-built mark-ups | Requests inspection; cannot self-approve |
| Laboratory / third party | Samples, tests and reports to the specified standards | Reports independently to the consultant |
| Document Control | Registers, distributes and archives every record with a unique number | Refuses uncontrolled documents |
H = hold point (work may not proceed without the consultant's witnessed approval) · W = witness point (notified; may proceed if the consultant does not attend) · S = surveillance (records reviewed).
| # | Activity | Inspection / test | Reference | Type | Record |
|---|---|---|---|---|---|
| 1 | Setting-out | Grid, benchmarks and levels verified against the survey | Drawings, survey data | H | Signed setting-out sheet |
| 2 | Excavation | Bottom level, bearing stratum, dimensions | Soil report, drawings | H | Inspection record |
| 3 | Blinding / formation | Level and cleanliness before reinforcement | Spec. §03300 | W | Inspection record |
| 4 | Reinforcement | Bar size, spacing, laps, cover, chairs | BBS, structural drawings | H | Reinforcement checklist |
| 5 | Formwork | Line, level, plumb, tightness, release agent | Drawings | W | Formwork checklist |
| 6 | Concrete placement | Slump, temperature, age, cube sampling, vibration | Spec., mix design | H | Pour card + cube register |
| 7 | Backfill | Layer thickness, moisture, field density | Spec. §31200 | W | Density test report |
| 8 | Blockwork | Alignment, plumb, mortar mix, movement joints, ties | Spec., drawings | S | Inspection record |
| 9 | Waterproofing | Surface prep, laps, flood test 24 h | Spec., manufacturer | H | Flood test certificate |
| 10 | MEP pressure tests | Test pressure, duration, drop | Spec., code | H | Signed test sheet |
| 11 | Electrical tests | Insulation resistance, continuity, earth loop | IEC 60364 | W | Test certificate per circuit |
| 12 | Finishes mock-up | Flatness, adhesion, colour, workmanship | Spec., approved sample | H | Mock-up acceptance |
Any non-conforming work is tagged and, where it affects safety or durability, stopped immediately by the QA/QC engineer. The tag stays until the disposition is closed.
NCR number, date, location, description, specification clause breached, and the immediate containment action. Photographs are attached; the NCR is issued within 24 hours of identification.
One of: rework to specification, repair by an approved method, accept with the consultant's written concession, or reject and remove. Structural dispositions require the structural engineer's written agreement — the contractor cannot self-accept a structural deviation.
Stated in one sentence naming the process failure, not the person. "Spacer density not specified in the method statement" is a root cause; "operator error" is not.
A change to the method statement, the checklist or the training record that prevents recurrence, with an owner and a date.
Re-inspection confirms the fix; the closure is signed and the NCR log updated. An NCR closed without re-inspection is not closed.
| NCR no. | Date | Location / element | Description | Disposition | Closed | Verified by |
|---|---|---|---|---|---|---|
Every record carries a unique number of the form PROJECT-DISC-SEQ-REV and is filed against the element it concerns, so that a future query about one column can be answered without searching the project. Records are retained for the period stated in the contract and handed over as part of the closeout document set: inspection records, test certificates, cube results, NCR log, material approvals and commissioning reports.
| Frequency | Activity | Output |
|---|---|---|
| Weekly | Quality walk with the consultant, open NCR review | Minutes and action list |
| Monthly | Internal audit of one process (rotating) | Audit report with findings |
| Monthly | Quality KPI report to the project manager | Objective dashboard |
| Quarterly | System review against the certified QMS | Management review record |
| At handover | Final record audit before the handover package is issued | Signed completeness certificate |