Form TP-04 · Quality Assurance & Quality Control Plan

Quality Assurance and Quality Control Plan (QA/QC)

Who owns quality, which inspections are hold points, what happens when work fails, and how records prove it afterwards.

Sections7
Hold points6
ITP items12
Rev.A
What evaluators look for: not a policy statement, but a named quality engineer, a table of inspection and test points with the inspection authority marked, and a non-conformance procedure that has teeth. A plan without hold points is a hope, not a plan.

1 Quality Policy and Objectives

We deliver the Works to the specification, first time, and we prove it with records. The quality system on this project is a project-specific plan subordinate to our certified quality management system and is auditable against it. Conformance is verified by inspection and test before work is covered, not by retrospective argument after it is rejected.

#ObjectiveTargetVerification
1First-time acceptance of structural inspections≥ 95%Inspection register
2Non-conformances closed within 14 days100%NCR log
3Concrete cube results meeting the specified class≥ 97.5% at 28 daysCube test register
4Services pressure tests passed first attempt≥ 90%Test sheets
5Snags per unit at handover≤ 3Snag list
6Document transmittals acknowledged within 3 working days100%Transmittal log

2 Quality Organisation and Responsibilities

Project ManagerAccountable for quality performance
QA/QC EngineerIndependent of production
Site EngineerInspection requests
Lab & TestingCubes, density, pressure
Document ControlRecords & transmittals
RoleQuality responsibilityAuthority
Project ManagerOwns the QA/QC plan, chairs the weekly quality meeting, approves NCR dispositionStops work on any non-conforming activity
QA/QC EngineerIssues inspection requests, witnesses hold points, maintains registers, raises NCRsRejects work; may not be overruled by production
Site EngineerRaises inspection requests ahead of covering work, maintains as-built mark-upsRequests inspection; cannot self-approve
Laboratory / third partySamples, tests and reports to the specified standardsReports independently to the consultant
Document ControlRegisters, distributes and archives every record with a unique numberRefuses uncontrolled documents

3 Inspection and Test Plan (ITP)

H = hold point (work may not proceed without the consultant's witnessed approval)  ·  W = witness point (notified; may proceed if the consultant does not attend)  ·  S = surveillance (records reviewed).

#ActivityInspection / testReferenceTypeRecord
1Setting-outGrid, benchmarks and levels verified against the surveyDrawings, survey dataHSigned setting-out sheet
2ExcavationBottom level, bearing stratum, dimensionsSoil report, drawingsHInspection record
3Blinding / formationLevel and cleanliness before reinforcementSpec. §03300WInspection record
4ReinforcementBar size, spacing, laps, cover, chairsBBS, structural drawingsHReinforcement checklist
5FormworkLine, level, plumb, tightness, release agentDrawingsWFormwork checklist
6Concrete placementSlump, temperature, age, cube sampling, vibrationSpec., mix designHPour card + cube register
7BackfillLayer thickness, moisture, field densitySpec. §31200WDensity test report
8BlockworkAlignment, plumb, mortar mix, movement joints, tiesSpec., drawingsSInspection record
9WaterproofingSurface prep, laps, flood test 24 hSpec., manufacturerHFlood test certificate
10MEP pressure testsTest pressure, duration, dropSpec., codeHSigned test sheet
11Electrical testsInsulation resistance, continuity, earth loopIEC 60364WTest certificate per circuit
12Finishes mock-upFlatness, adhesion, colour, workmanshipSpec., approved sampleHMock-up acceptance

4 Material and Procurement Control

5 Non-Conformance (NCR) and Corrective Action

  1. Identify and segregate

    Any non-conforming work is tagged and, where it affects safety or durability, stopped immediately by the QA/QC engineer. The tag stays until the disposition is closed.

  2. Raise the NCR

    NCR number, date, location, description, specification clause breached, and the immediate containment action. Photographs are attached; the NCR is issued within 24 hours of identification.

  3. Disposition

    One of: rework to specification, repair by an approved method, accept with the consultant's written concession, or reject and remove. Structural dispositions require the structural engineer's written agreement — the contractor cannot self-accept a structural deviation.

  4. Root cause

    Stated in one sentence naming the process failure, not the person. "Spacer density not specified in the method statement" is a root cause; "operator error" is not.

  5. Corrective action

    A change to the method statement, the checklist or the training record that prevents recurrence, with an owner and a date.

  6. Verify and close

    Re-inspection confirms the fix; the closure is signed and the NCR log updated. An NCR closed without re-inspection is not closed.

NCR no.DateLocation / elementDescriptionDispositionClosedVerified by

6 Document and Record Control

Every record carries a unique number of the form PROJECT-DISC-SEQ-REV and is filed against the element it concerns, so that a future query about one column can be answered without searching the project. Records are retained for the period stated in the contract and handed over as part of the closeout document set: inspection records, test certificates, cube results, NCR log, material approvals and commissioning reports.

7 Internal Audit and Reporting

FrequencyActivityOutput
WeeklyQuality walk with the consultant, open NCR reviewMinutes and action list
MonthlyInternal audit of one process (rotating)Audit report with findings
MonthlyQuality KPI report to the project managerObjective dashboard
QuarterlySystem review against the certified QMSManagement review record
At handoverFinal record audit before the handover package is issuedSigned completeness certificate
QA/QC engineer
Project manager
Quality manager