Forms TP-10 to TP-13 · Supporting Forms

Supporting Forms: Tender Checklist, RFI, Deviations & Value Engineering, Handover Warranty

The four forms that prevent the most common causes of rejection, dispute and unpaid closeout claims.

Forms4
Checklist items22
Sections4
Rev.A
Sequence matters: fill TP-10 before you price, TP-11 and TP-12 before you submit, and TP-13 at handover. A deviations schedule raised after award is a variation; raised before submission it is a qualified offer you can defend.

TP-10 Tender Document Checklist

Tick each item before packing. A missing mandatory item is an administrative rejection that no technical score can recover.

#Document / requirementTypeStatusOwnerNotes
1Signed and stamped cover letterMandatory
2Bid bond / tender securityMandatory
3Commercial registrationMandatory
4Contractor classification certificateMandatory
5Contractors' association membershipMandatory
6Social security clearanceMandatory
7Tax compliance certificateMandatory
8Methodology and scope understanding (TP-02)Mandatory
9Time schedule and bar chart (TP-03)Mandatory
10QA/QC plan (TP-04)Mandatory
11HSE plan (TP-05)Mandatory
12Organisation chart and CVs (TP-06)Scored
13Equipment schedule (TP-06)Scored
14Track record and certificates (TP-07)Scored
15Risk register (TP-08)Scored
16Priced BOQ, all items and totals (TP-09)Mandatory
17Financial offer letterMandatory
18Deviations / qualifications schedule (TP-12)Scored
19Audited financial statements, 3 yearsMandatory
20Bank reference / line of creditScored
21ISO certificates with scopeScored
22Addenda acknowledgementMandatory

Before you seal the envelope

Count the copies, confirm the original is marked as such, check every signature and stamp, verify that the pricing in words and figures agree, and confirm the submission address and time. Late is late — there is no discretion, and a courier timestamp is not the Employer's clock.

TP-11 Request for Information / Clarification

RFI no.SubjectDate raisedResponse dueResponse dateStatus

RFI discipline

One question per RFI. A document with six questions gets one answer to three of them. Closing date for questions is stated in the instructions — an RFI raised after that date will not be answered and its subject becomes your risk at the price you bid.

TP-12 Deviations & Value Engineering

Record every departure from the specification, and every alternative you propose with its saving. An unlisted departure is deemed included at no extra cost.

A · Deviations

#Specification clauseRequirementBidder's proposalReasonCost effectTime effect
1
2
3
4

B · Value engineering proposals

#ElementSpecified solutionProposed alternativeSavingEffect on performance / warranty
1
2
3

How to make a VE proposal acceptable

A value engineering proposal is accepted on three conditions: it does not reduce performance or design life, it carries an equivalent or better warranty, and the saving is shared or passed on as the contract requires. A proposal that offers a saving but weakens the specification will be rejected and will damage the credibility of your other submissions.

TP-13 Quality & Handover Warranty

Element / systemWarranty periodProviderDocument referenceAttached
Structural works10 years (or as specified)Contractor
Waterproofing / roofing10 yearsManufacturer + applicator
External envelope / glazing5 yearsManufacturer
Mechanical / HVAC equipment24 monthsManufacturer
Electrical installations24 monthsContractor
Fire detection & protection24 monthsManufacturer + contractor
Lifts24 monthsManufacturer
Finishes12 monthsContractor
Joinery & ironmongery12 monthsManufacturer
Document handed overCopiesFormatDate
As-built drawings2 + PDFDWG + PDF
O&M manuals2 + PDFHard + PDF
Warranty certificates1 setHard + PDF
Test and commissioning reports1 setPDF
Spare parts & attic stockAs scheduledPhysical
Keys and access cardsAs scheduledPhysical + register
Training records1 setSigned attendance
Project manager
Authorised representative