Quantities carried from the take-off sheet, priced per item, with waste, overhead, profit and tax shown as separate lines. Change the currency in the top bar and every figure converts; change a rate and every total follows.
Items24
Groups9
Overhead12%
Profit8%
How to price this form: enter the unit rate only. The amount, the group subtotals and the offer value are calculated. The rates currently shown are illustrative — they exist to demonstrate the arithmetic and must be replaced with live supplier and subcontract quotations before submission. The quantities are not illustrative: they are derived from the declared geometry of the worked example and can be verified by hand from the dimensions in each row.
1 Pricing Factors
2 Detailed Price Schedule
Net quantity = length × width × height × number.
Gross quantity applies the waste percentage. Amount = gross quantity × unit rate.
Code
Description
Unit
L
W
H
No.
Net
Waste %
Gross
Amount
Rate
01 · EARTHWORKS & BACKFILL
01-01
Excavation for foundations
m³
116.160
116.160
1,068.67
01-02
Backfilling & compaction
m³
81.296
89.426
380.06
02 · CONCRETE WORKS
02-01
Blinding concrete C15
m³
4.624
4.855
582.62
02-02a
Isolated footings C30
m³
14.400
14.832
2,343.46
02-02b
Tie beams C30
m³
15.840
16.315
2,577.80
02-02c
Columns C30
m³
12.288
12.657
1,999.75
02-02d
Beams C30
m³
22.000
22.660
3,580.28
02-02e
Slabs C30
m³
54.000
55.620
8,787.96
03 · REINFORCEMENT
03-01
High-yield reinforcement B420
t
11.248
11.698
11,405.72
04 · FORMWORK
04-01
Formwork — sides, soffits and slabs
m²
893.760
938.448
5,959.14
05 · MASONRY
05-01
Lightweight blockwork
m²
522.480
553.829
11,353.49
06 · PLASTER & PAINT
06-01
Cement plaster
m²
1,668.960
1,802.477
13,969.20
06-02
Emulsion paint
m²
1,668.960
1,752.408
7,885.84
07 · TILING
07-01
Floor tiles 600×600
m²
240.000
264.000
6,705.60
07-02
Wall tiles
m²
180.000
198.000
4,474.80
07-03
Skirting
m
150.000
160.500
2,038.35
08 · ELECTRICAL
08-01
Lighting & socket points
no.
168.000
171.360
5,312.16
08-02
Cable installations
m
1,850.000
1,998.000
10,689.30
08-03
Conduits & trunking
m
1,600.000
1,728.000
3,888.00
08-04
Distribution boards
no.
4.000
4.000
820.00
09 · MECHANICAL & PLUMBING
09-01
Copper A/C refrigerant pipework
m
220.000
233.200
4,104.32
09-02
PVC drainage
m
120.000
128.400
1,521.54
09-03
PPR water supply
m
260.000
278.200
2,434.25
09-04
Sanitary sets
set
12.000
12.000
3,132.00
Total direct cost
117,014.31
3 Summary and Offer Value
Work group
Amount
Share
Earthworks & backfill
1,448.73
1.2%
Concrete works
19,871.87
17.0%
Reinforcement
11,405.72
9.7%
Formwork
5,959.14
5.1%
Masonry & blockwork
11,353.49
9.7%
Plaster & paint
21,855.04
18.7%
Tiling & flooring
13,218.75
11.3%
Electrical
20,709.46
17.7%
Mechanical & plumbing
11,192.11
9.6%
Total direct cost
117,014.31
100%
Build-up of offer value
Rate
Amount
Direct cost (including waste)
—
117,014.31
Overhead & site establishment
12.0%
14,041.72
Subtotal after overhead
—
131,056.03
Profit
8.0%
10,484.48
Subtotal before tax
—
141,540.51
Tax / VAT
0.0%
0.00
Offer value
—
141,540.51
Consistency checks before submission
Group subtotals here must equal the Summary sheet totals in Form TP-14.
The offer value must match the figure written in the financial offer and the cover letter.
Payment percentages in TP-03 must be defensible from these group shares.
Any group above 20% of the total deserves a second look at its rates.
4 Item Allocation by Stage
Links each work group to the milestone at which it is earned. "
This is the bridge between the price schedule and the payment schedule.
Work group
Milestone
Earned at
Earthworks & backfill
M2
Substructure complete
Concrete works
M2–M4
Substructure and superstructure
Reinforcement
M2–M4
Substructure and superstructure
Formwork
M2–M4
Substructure and superstructure
Masonry & blockwork
M3–M6
Superstructure complete
Plaster & paint
M4–M5
Envelope & first fix complete
Tiling & flooring
M5
Substantial completion
Electrical
M4–M5
Substantial completion
Mechanical & plumbing
M4–M5
Substantial completion
Quantity surveyor
Commercial manager
General manager
FORM TP-09 · MMC Technical Proposal Kit — English Edition v2.0TP-KIT v2.0 · English Edition