Form TP-09 · BOQ Summary & Price Schedule

Bill of Quantities Summary and Price Schedule

Quantities carried from the take-off sheet, priced per item, with waste, overhead, profit and tax shown as separate lines. Change the currency in the top bar and every figure converts; change a rate and every total follows.

Items24
Groups9
Overhead12%
Profit8%
How to price this form: enter the unit rate only. The amount, the group subtotals and the offer value are calculated. The rates currently shown are illustrative — they exist to demonstrate the arithmetic and must be replaced with live supplier and subcontract quotations before submission. The quantities are not illustrative: they are derived from the declared geometry of the worked example and can be verified by hand from the dimensions in each row.

1 Pricing Factors

2 Detailed Price Schedule

Net quantity = length × width × height × number. Gross quantity applies the waste percentage. Amount = gross quantity × unit rate.

Code Description Unit L W H No. Net Waste % Gross Amount Rate
01 · EARTHWORKS & BACKFILL
01-01 Excavation for foundations m³ 116.160 116.160 1,068.67
01-02 Backfilling & compaction m³ 81.296 89.426 380.06
02 · CONCRETE WORKS
02-01 Blinding concrete C15 m³ 4.624 4.855 582.62
02-02a Isolated footings C30 m³ 14.400 14.832 2,343.46
02-02b Tie beams C30 m³ 15.840 16.315 2,577.80
02-02c Columns C30 m³ 12.288 12.657 1,999.75
02-02d Beams C30 m³ 22.000 22.660 3,580.28
02-02e Slabs C30 m³ 54.000 55.620 8,787.96
03 · REINFORCEMENT
03-01 High-yield reinforcement B420 t 11.248 11.698 11,405.72
04 · FORMWORK
04-01 Formwork — sides, soffits and slabs m² 893.760 938.448 5,959.14
05 · MASONRY
05-01 Lightweight blockwork m² 522.480 553.829 11,353.49
06 · PLASTER & PAINT
06-01 Cement plaster m² 1,668.960 1,802.477 13,969.20
06-02 Emulsion paint m² 1,668.960 1,752.408 7,885.84
07 · TILING
07-01 Floor tiles 600×600 m² 240.000 264.000 6,705.60
07-02 Wall tiles m² 180.000 198.000 4,474.80
07-03 Skirting m 150.000 160.500 2,038.35
08 · ELECTRICAL
08-01 Lighting & socket points no. 168.000 171.360 5,312.16
08-02 Cable installations m 1,850.000 1,998.000 10,689.30
08-03 Conduits & trunking m 1,600.000 1,728.000 3,888.00
08-04 Distribution boards no. 4.000 4.000 820.00
09 · MECHANICAL & PLUMBING
09-01 Copper A/C refrigerant pipework m 220.000 233.200 4,104.32
09-02 PVC drainage m 120.000 128.400 1,521.54
09-03 PPR water supply m 260.000 278.200 2,434.25
09-04 Sanitary sets set 12.000 12.000 3,132.00
Total direct cost117,014.31

3 Summary and Offer Value

Work groupAmountShare
Earthworks & backfill1,448.731.2%
Concrete works19,871.8717.0%
Reinforcement11,405.729.7%
Formwork5,959.145.1%
Masonry & blockwork11,353.499.7%
Plaster & paint21,855.0418.7%
Tiling & flooring13,218.7511.3%
Electrical20,709.4617.7%
Mechanical & plumbing11,192.119.6%
Total direct cost117,014.31100%
Build-up of offer valueRateAmount
Direct cost (including waste)—117,014.31
Overhead & site establishment12.0%14,041.72
Subtotal after overhead—131,056.03
Profit8.0%10,484.48
Subtotal before tax—141,540.51
Tax / VAT0.0%0.00
Offer value—141,540.51

Consistency checks before submission

  • Group subtotals here must equal the Summary sheet totals in Form TP-14.
  • The offer value must match the figure written in the financial offer and the cover letter.
  • Payment percentages in TP-03 must be defensible from these group shares.
  • Any group above 20% of the total deserves a second look at its rates.

4 Item Allocation by Stage

Links each work group to the milestone at which it is earned. " This is the bridge between the price schedule and the payment schedule.

Work groupMilestoneEarned at
Earthworks & backfillM2Substructure complete
Concrete worksM2–M4Substructure and superstructure
ReinforcementM2–M4Substructure and superstructure
FormworkM2–M4Substructure and superstructure
Masonry & blockworkM3–M6Superstructure complete
Plaster & paintM4–M5Envelope & first fix complete
Tiling & flooringM5Substantial completion
ElectricalM4–M5Substantial completion
Mechanical & plumbingM4–M5Substantial completion