Dimensions in, quantities out. Every figure below is computed from the length, width, height, number and waste percentage in its own row — change a dimension and the quantity, the group subtotal and the total all follow.
Net = L × W × H × No. · Gross = Net × (1 + waste%). · Waste is applied per row because it differs by material: rebar 4%, concrete 3%, blockwork 6%, tiles 10%. · Value = Gross × the BOQ rate carried from TP-09.
| Code | Description of works | Unit | L | W | H / D | No. | Net qty | Waste % | Gross qty | Value |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 · EARTHWORKS & BACKFILL | ||||||||||
| 01-01 | Excavation for foundations | m³ | 116.160 | 116.160 | 1,068.67 | |||||
| 01-02 | Backfilling & compaction | m³ | 81.296 | 89.426 | 380.06 | |||||
| 02 · CONCRETE WORKS | ||||||||||
| 02-01 | Blinding concrete C15 | m³ | 4.624 | 4.855 | 582.62 | |||||
| 02-02a | Isolated footings C30 | m³ | 14.400 | 14.832 | 2,343.46 | |||||
| 02-02b | Tie beams C30 | m³ | 15.840 | 16.315 | 2,577.80 | |||||
| 02-02c | Columns C30 | m³ | 12.288 | 12.657 | 1,999.75 | |||||
| 02-02d | Beams C30 | m³ | 22.000 | 22.660 | 3,580.28 | |||||
| 02-02e | Slabs C30 | m³ | 54.000 | 55.620 | 8,787.96 | |||||
| 03 · REINFORCEMENT | ||||||||||
| 03-01 | High-yield reinforcement B420 | t | 11.248 | 11.698 | 11,405.72 | |||||
| 04 · FORMWORK | ||||||||||
| 04-01 | Formwork — sides, soffits and slabs | m² | 893.760 | 938.448 | 5,959.14 | |||||
| 05 · MASONRY | ||||||||||
| 05-01 | Lightweight blockwork | m² | 522.480 | 553.829 | 11,353.49 | |||||
| 06 · PLASTER & PAINT | ||||||||||
| 06-01 | Cement plaster | m² | 1,668.960 | 1,802.477 | 13,969.20 | |||||
| 06-02 | Emulsion paint | m² | 1,668.960 | 1,752.408 | 7,885.84 | |||||
| 07 · TILING | ||||||||||
| 07-01 | Floor tiles 600×600 | m² | 240.000 | 264.000 | 6,705.60 | |||||
| 07-02 | Wall tiles | m² | 180.000 | 198.000 | 4,474.80 | |||||
| 07-03 | Skirting | m | 150.000 | 160.500 | 2,038.35 | |||||
| 08 · ELECTRICAL | ||||||||||
| 08-01 | Lighting & socket points | no. | 168.000 | 171.360 | 5,312.16 | |||||
| 08-02 | Cable installations | m | 1,850.000 | 1,998.000 | 10,689.30 | |||||
| 08-03 | Conduits & trunking | m | 1,600.000 | 1,728.000 | 3,888.00 | |||||
| 08-04 | Distribution boards | no. | 4.000 | 4.000 | 820.00 | |||||
| 09 · MECHANICAL & PLUMBING | ||||||||||
| 09-01 | Copper A/C refrigerant pipework | m | 220.000 | 233.200 | 4,104.32 | |||||
| 09-02 | PVC drainage | m | 120.000 | 128.400 | 1,521.54 | |||||
| 09-03 | PPR water supply | m | 260.000 | 278.200 | 2,434.25 | |||||
| 09-04 | Sanitary sets | set | 12.000 | 12.000 | 3,132.00 | |||||
| Total measured value at BOQ rates | 117,014.31 | |||||||||
Group subtotals carried to the BOQ. The share column is what tells you where to focus a pricing review: a group above 20% of the total deserves a second check of both quantity and rate.
| Work group | Value at BOQ rates | Share |
|---|---|---|
| Earthworks & backfill | 1,448.73 | 1.2% |
| Concrete works | 19,871.87 | 17.0% |
| Reinforcement | 11,405.72 | 9.7% |
| Formwork | 5,959.14 | 5.1% |
| Masonry & blockwork | 11,353.49 | 9.7% |
| Plaster & paint | 21,855.04 | 18.7% |
| Tiling & flooring | 13,218.75 | 11.3% |
| Electrical | 20,709.46 | 17.7% |
| Mechanical & plumbing | 11,192.11 | 9.6% |
| Total | 117,014.31 | 100% |
| Cross-check | TP-14 | TP-09 |
|---|---|---|
| Total direct cost | 117,014.31 | 117,014.31 |
| After overhead 12% | 131,056.03 | 131,056.03 |
| Offer value | 141,540.51 | 141,540.51 |
The difference is almost always one of: a row measured here but not priced in the BOQ (an omission), a row priced in the BOQ but not measured here (a duplicate), or a different waste percentage in the two places. Find the row before you change a total.
| Material | Waste applied | Basis | Note |
|---|---|---|---|
| Reinforcement | 4% | Cutting and lap allowance | Add laps separately; this covers offcut only |
| Concrete | 3% | Over-pour and spillage | Higher on small sections and pumped pours |
| Formwork | 5% | Damage and re-use loss | Depends on the number of re-uses planned |
| Blockwork | 6% | Cutting at openings and corners | Rises with the number of openings |
| Plaster | 8% | Thickness variation and waste | Applies to the mortar, not the area |
| Paint | 5% | Application loss | Per coat — multiply by the number of coats |
| Tiles | 10% | Cutting and pattern | Diagonal or patterned layouts need 15% |
| Pipe and cable | 6–8% | Slack, bends and terminations | Cable also needs a route-length factor, not only waste |
The figures on this sheet come from the worked example in Guide TP-G1: a 12.0 × 10.0 m residential building on a 6.0 m grid, 16 footings, 32 columns, three suspended slabs. Two independent checks:
| Blinding 1.70×1.70×0.10×16 | 4.624 m³ |
| Footings 1.50×1.50×0.40×16 | 14.400 m³ |
| Tie beams 0.30×0.60×88 | 15.840 m³ |
| Columns 0.30×0.40×3.20×32 | 12.288 m³ |
| Beams 0.25×0.50×88×2 | 22.000 m³ |
| Slabs 12×10×0.15×3 | 54.000 m³ |
| Sum | 123.15 m³ |
11.248 t over 123.15 m³ of structural concrete (excluding blinding, which is unreinforced) gives 91 kg/m³. For a residential frame this sits inside the normal 90–130 kg/m³ band — low but not implausible for light slabs on a regular grid.
A result outside 80–150 kg/m³ on a building of this type means the schedule has been misread, a diameter omitted, or laps left out. Use this ratio as a red flag, never as the quantity.