M MMC Technical Proposal Kit
FORM TP-14
🔓 MMC Portal Index ← PrevNext →
AR
Form TP-14 · Quantity Take-off & Summary Sheet

Quantity Take-off Sheet and Summary Sheet

Dimensions in, quantities out. Every figure below is computed from the length, width, height, number and waste percentage in its own row — change a dimension and the quantity, the group subtotal and the total all follow.

Items24
Groups9
SummaryLinked
Rev.A
This sheet is the source; the BOQ is the destination. Quantities measured here must appear unchanged in Form TP-09. If the two disagree, one of them is wrong and the evaluator will find it. The cross-check at the foot of this page must agree with TP-09 to the cent.

1 Sheet Particulars

2 Take-off Sheet

Net = L × W × H × No.  ·  Gross = Net × (1 + waste%).  ·  Waste is applied per row because it differs by material: rebar 4%, concrete 3%, blockwork 6%, tiles 10%.  ·  Value = Gross × the BOQ rate carried from TP-09.

Code Description of works Unit L W H / D No. Net qty Waste % Gross qty Value
01 · EARTHWORKS & BACKFILL
01-01 Excavation for foundations m³ 116.160 116.160 1,068.67
01-02 Backfilling & compaction m³ 81.296 89.426 380.06
02 · CONCRETE WORKS
02-01 Blinding concrete C15 m³ 4.624 4.855 582.62
02-02a Isolated footings C30 m³ 14.400 14.832 2,343.46
02-02b Tie beams C30 m³ 15.840 16.315 2,577.80
02-02c Columns C30 m³ 12.288 12.657 1,999.75
02-02d Beams C30 m³ 22.000 22.660 3,580.28
02-02e Slabs C30 m³ 54.000 55.620 8,787.96
03 · REINFORCEMENT
03-01 High-yield reinforcement B420 t 11.248 11.698 11,405.72
04 · FORMWORK
04-01 Formwork — sides, soffits and slabs m² 893.760 938.448 5,959.14
05 · MASONRY
05-01 Lightweight blockwork m² 522.480 553.829 11,353.49
06 · PLASTER & PAINT
06-01 Cement plaster m² 1,668.960 1,802.477 13,969.20
06-02 Emulsion paint m² 1,668.960 1,752.408 7,885.84
07 · TILING
07-01 Floor tiles 600×600 m² 240.000 264.000 6,705.60
07-02 Wall tiles m² 180.000 198.000 4,474.80
07-03 Skirting m 150.000 160.500 2,038.35
08 · ELECTRICAL
08-01 Lighting & socket points no. 168.000 171.360 5,312.16
08-02 Cable installations m 1,850.000 1,998.000 10,689.30
08-03 Conduits & trunking m 1,600.000 1,728.000 3,888.00
08-04 Distribution boards no. 4.000 4.000 820.00
09 · MECHANICAL & PLUMBING
09-01 Copper A/C refrigerant pipework m 220.000 233.200 4,104.32
09-02 PVC drainage m 120.000 128.400 1,521.54
09-03 PPR water supply m 260.000 278.200 2,434.25
09-04 Sanitary sets set 12.000 12.000 3,132.00
Total measured value at BOQ rates117,014.31

3 Summary Sheet

Group subtotals carried to the BOQ. The share column is what tells you where to focus a pricing review: a group above 20% of the total deserves a second check of both quantity and rate.

Work groupValue at BOQ ratesShare
Earthworks & backfill1,448.731.2%
Concrete works19,871.8717.0%
Reinforcement11,405.729.7%
Formwork5,959.145.1%
Masonry & blockwork11,353.499.7%
Plaster & paint21,855.0418.7%
Tiling & flooring13,218.7511.3%
Electrical20,709.4617.7%
Mechanical & plumbing11,192.119.6%
Total117,014.31100%
Cross-checkTP-14TP-09
Total direct cost117,014.31117,014.31
After overhead 12%131,056.03131,056.03
Offer value141,540.51141,540.51

If the two columns disagree

The difference is almost always one of: a row measured here but not priced in the BOQ (an omission), a row priced in the BOQ but not measured here (a duplicate), or a different waste percentage in the two places. Find the row before you change a total.

4 Waste Analysis

MaterialWaste appliedBasisNote
Reinforcement4%Cutting and lap allowanceAdd laps separately; this covers offcut only
Concrete3%Over-pour and spillageHigher on small sections and pumped pours
Formwork5%Damage and re-use lossDepends on the number of re-uses planned
Blockwork6%Cutting at openings and cornersRises with the number of openings
Plaster8%Thickness variation and wasteApplies to the mortar, not the area
Paint5%Application lossPer coat — multiply by the number of coats
Tiles10%Cutting and patternDiagonal or patterned layouts need 15%
Pipe and cable6–8%Slack, bends and terminationsCable also needs a route-length factor, not only waste

5 Verification of the Worked Example

The figures on this sheet come from the worked example in Guide TP-G1: a 12.0 × 10.0 m residential building on a 6.0 m grid, 16 footings, 32 columns, three suspended slabs. Two independent checks:

Check 1 — concrete by element

Blinding 1.70×1.70×0.10×164.624 m³
Footings 1.50×1.50×0.40×1614.400 m³
Tie beams 0.30×0.60×8815.840 m³
Columns 0.30×0.40×3.20×3212.288 m³
Beams 0.25×0.50×88×222.000 m³
Slabs 12×10×0.15×354.000 m³
Sum123.15 m³

Check 2 — reinforcement per cubic metre

11.248 t over 123.15 m³ of structural concrete (excluding blinding, which is unreinforced) gives 91 kg/m³. For a residential frame this sits inside the normal 90–130 kg/m³ band — low but not implausible for light slabs on a regular grid.

A result outside 80–150 kg/m³ on a building of this type means the schedule has been misread, a diameter omitted, or laps left out. Use this ratio as a red flag, never as the quantity.

Quantity surveyor
Chief estimator
Commercial manager