The order of work matters as much as the content. Fill in this sequence and the documents will agree with each other.
| Code | Document | Fill it when | Feeds |
|---|---|---|---|
| TP-01 | Cover letter & compliance statement | Last, before sealing | The whole offer |
| TP-02 | Scope understanding & methodology | First | TP-03, TP-04, TP-05 |
| TP-03 | Time schedule & payment schedule | After TP-09 groups are known | Financial offer |
| TP-04 | QA/QC plan | Alongside TP-02 | Closeout obligations |
| TP-05 | HSE plan | Alongside TP-02 | Site mobilisation |
| TP-06 | Resource plan (org, CVs, plant, materials) | Early — it takes the longest | TP-03 credibility |
| TP-07 | Track record | Early — certificates must be requested | Prequalification score |
| TP-08 | Risk register | After TP-02 | Pricing contingency |
| TP-09 | BOQ summary & price schedule | After TP-14 | Financial offer, TP-03 |
| TP-10–13 | Tender checklist, RFI, deviations, handover warranty | Checklist first, warranty at handover | Submission completeness |
| TP-14 | Quantity take-off & summary | Before TP-09 | TP-09 |
| TP-G1 | Drawing reading guide | While measuring | TP-14 |
| TP-G2 | This guide | Before starting | — |
Instructions, conditions, specification, drawings, BOQ and every addendum. Then read the drawing register and confirm which revisions are current. An offer built on a superseded drawing is worthless however well written.
This tells you what must be produced and what must be requested from other people — certificates, references, audited accounts. Those take days; start them now.
Every quantity traced to a drawing number, revision and dimension. Do not price anything until the take-off is complete, or you will price the same item twice.
Enter unit rates, apply waste and the overhead and profit factors. The offer value emerges from the arithmetic — do not decide the offer value first and back-fill rates.
The methodology must describe the project you have just measured. Specificity here is what separates a scored submission from a rejected one.
Names, plant, sources, references and risks. Each must be verifiable, and none may be repeated from another tender without checking it is still true.
Payment percentages must follow the value of the work, not a preferred cash flow. If the programme and the payment ladder disagree, the evaluator sees it immediately.
Every departure recorded before submission; anything unresolved becomes your risk at the price you bid.
The cover letter summarises an offer that now exists. Check that the figure in the letter matches TP-09 to the last digit.
The chain is deliberately linear, and each link is checkable:
A payment schedule written before the BOQ was priced. It always over-weights early milestones, because mobilisation feels expensive when you are staring at an empty site. It is not: on a building project, mobilisation is typically 3–5% of the contract value. If TP-03 claims 15% at mobilisation, the evaluator will query it, and if it is accepted the employer will query it again at the first payment certificate.
Three reviews, by three different people, in this order. A single reviewer catches layout errors; three catch arithmetic, omissions and inconsistencies.
| Review | Reviewer | Checks | Signature |
|---|---|---|---|
| 1 — Technical | Technical manager / chief engineer | Scope complete, methodology matches the drawings, no discipline missing, TP-02 consistent with TP-04 and TP-05 | |
| 2 — Commercial | Quantity surveyor / commercial manager | Every BOQ item priced, no zero rates, waste applied once, TP-14 and TP-09 agree to the cent, offer value matches the financial letter | |
| 3 — Administrative | Contracts / proposals manager | TP-10 checklist complete, all signatures and stamps, bonds and certificates current, additions acknowledged, copies counted, deadline confirmed |
| # | Check | Where | ✓ |
|---|---|---|---|
| 1 | BOQ total equals the TP-14 summary total | TP-09 / TP-14 | |
| 2 | Offer value in TP-01 equals the financial offer letter | TP-01 | |
| 3 | Payment percentages in TP-03 sum to 100% | TP-03 | |
| 4 | Milestone values are defensible from the BOQ group shares | TP-03 / TP-09 | |
| 5 | No item has a zero or blank rate | TP-09 | |
| 6 | Waste applied once, not twice | TP-09 / TP-14 | |
| 7 | Every deviation appears in TP-12 as well as TP-01 | TP-12 | |
| 8 | Programme duration matches the stated construction period | TP-03 | |
| 9 | Key personnel not double-booked against another live tender | TP-06 | |
| 10 | Every certificate cited in TP-07 is attached and current | TP-07 | |
| 11 | All addenda acknowledged | TP-10 | |
| 12 | Bid bond amount, form and validity correct | TP-10 | |
| 13 | Signed, stamped, dated on every form that requires it | All | |
| 14 | Currency stated consistently throughout | All | |
| 15 | Correct number of copies, original marked | Submission |
| Reason | How it happens | How this kit prevents it |
|---|---|---|
| Missing mandatory document | Checklist not used; certificate expired | TP-10 with an owner and status per line |
| Unsigned or unstamped form | Signed the PDF, not the page | Signature blocks on every form that needs one |
| Arithmetic inconsistency between documents | Offer value typed by hand into three places | One calculated value; TP-14 and TP-09 cross-check to the cent |
| Unqualified departure | Deviation stated in the cover letter only | TP-12 deviations schedule, cross-referenced from TP-01 |
| Programme inconsistent with the price | Payment ladder written before pricing | TP-03 built from the priced BOQ groups |
| Generic methodology | Reused from another tender | TP-02 requires project-specific content per package |
| Late submission | Courier relied on to meet the deadline | Checklist deadline line, administrative review sign-off |
Every unit rate in TP-09 is illustrative. It exists to demonstrate the arithmetic of the chain from take-off to offer value, and it is not a market price. Before submission, replace every rate with a live supplier or subcontract quotation, and replace the overhead and profit factors with your own company figures. The quantities may be used as a worked example; the prices may not.