Guide TP-G2 · How to Use This Kit

How to Use the Kit: Filling the Forms, Pricing, and Reviewing Before Submission

The order of work matters as much as the content. Fill in this sequence and the documents will agree with each other.

Sections7
Forms13
Sheets7
Rev.A
Read this page first. The kit is not thirteen independent forms; it is one offer expressed thirteen ways. The quantities flow from TP-14 into TP-09, the payment percentages in TP-03 follow from the BOQ groups, and the methodology in TP-02 must match both. Fill them out of order and they will contradict each other in front of the evaluator.

1 What Is in the Kit

CodeDocumentFill it whenFeeds
TP-01Cover letter & compliance statementLast, before sealingThe whole offer
TP-02Scope understanding & methodologyFirstTP-03, TP-04, TP-05
TP-03Time schedule & payment scheduleAfter TP-09 groups are knownFinancial offer
TP-04QA/QC planAlongside TP-02Closeout obligations
TP-05HSE planAlongside TP-02Site mobilisation
TP-06Resource plan (org, CVs, plant, materials)Early — it takes the longestTP-03 credibility
TP-07Track recordEarly — certificates must be requestedPrequalification score
TP-08Risk registerAfter TP-02Pricing contingency
TP-09BOQ summary & price scheduleAfter TP-14Financial offer, TP-03
TP-10–13Tender checklist, RFI, deviations, handover warrantyChecklist first, warranty at handoverSubmission completeness
TP-14Quantity take-off & summaryBefore TP-09TP-09
TP-G1Drawing reading guideWhile measuringTP-14
TP-G2This guideBefore starting—

2 The Order of Work

  1. Read the tender documents completely, once, before writing anything

    Instructions, conditions, specification, drawings, BOQ and every addendum. Then read the drawing register and confirm which revisions are current. An offer built on a superseded drawing is worthless however well written.

  2. Complete TP-10, the tender checklist

    This tells you what must be produced and what must be requested from other people — certificates, references, audited accounts. Those take days; start them now.

  3. Measure, using TP-G1 and TP-14

    Every quantity traced to a drawing number, revision and dimension. Do not price anything until the take-off is complete, or you will price the same item twice.

  4. Price in TP-09

    Enter unit rates, apply waste and the overhead and profit factors. The offer value emerges from the arithmetic — do not decide the offer value first and back-fill rates.

  5. Write TP-02, then TP-04 and TP-05

    The methodology must describe the project you have just measured. Specificity here is what separates a scored submission from a rejected one.

  6. Fill TP-06, TP-07 and TP-08

    Names, plant, sources, references and risks. Each must be verifiable, and none may be repeated from another tender without checking it is still true.

  7. Build TP-03 from the priced BOQ

    Payment percentages must follow the value of the work, not a preferred cash flow. If the programme and the payment ladder disagree, the evaluator sees it immediately.

  8. Complete TP-12 (deviations) and TP-11 (any outstanding RFIs)

    Every departure recorded before submission; anything unresolved becomes your risk at the price you bid.

  9. Write TP-01 last and sign everything

    The cover letter summarises an offer that now exists. Check that the figure in the letter matches TP-09 to the last digit.

3 Linking Quantities to Prices

The chain is deliberately linear, and each link is checkable:

STEP 1
Measure
TP-14 · L × W × H × No., then waste
STEP 2
Summarise
TP-14 summary · 9 group subtotals
STEP 3
Price
TP-09 · rate per item, waste per row
STEP 4
Build up
Overhead 12% → profit 8% → tax
STEP 5
Distribute
TP-03 · payment % per milestone

The single most common internal inconsistency

A payment schedule written before the BOQ was priced. It always over-weights early milestones, because mobilisation feels expensive when you are staring at an empty site. It is not: on a building project, mobilisation is typically 3–5% of the contract value. If TP-03 claims 15% at mobilisation, the evaluator will query it, and if it is accepted the employer will query it again at the first payment certificate.

4 Filling the Forms in a Browser

5 Pre-Submission Review

Three reviews, by three different people, in this order. A single reviewer catches layout errors; three catch arithmetic, omissions and inconsistencies.

ReviewReviewerChecksSignature
1 — TechnicalTechnical manager / chief engineerScope complete, methodology matches the drawings, no discipline missing, TP-02 consistent with TP-04 and TP-05
2 — CommercialQuantity surveyor / commercial managerEvery BOQ item priced, no zero rates, waste applied once, TP-14 and TP-09 agree to the cent, offer value matches the financial letter
3 — AdministrativeContracts / proposals managerTP-10 checklist complete, all signatures and stamps, bonds and certificates current, additions acknowledged, copies counted, deadline confirmed

Final consistency checks — tick every one

#CheckWhere✓
1BOQ total equals the TP-14 summary totalTP-09 / TP-14
2Offer value in TP-01 equals the financial offer letterTP-01
3Payment percentages in TP-03 sum to 100%TP-03
4Milestone values are defensible from the BOQ group sharesTP-03 / TP-09
5No item has a zero or blank rateTP-09
6Waste applied once, not twiceTP-09 / TP-14
7Every deviation appears in TP-12 as well as TP-01TP-12
8Programme duration matches the stated construction periodTP-03
9Key personnel not double-booked against another live tenderTP-06
10Every certificate cited in TP-07 is attached and currentTP-07
11All addenda acknowledgedTP-10
12Bid bond amount, form and validity correctTP-10
13Signed, stamped, dated on every form that requires itAll
14Currency stated consistently throughoutAll
15Correct number of copies, original markedSubmission

6 Common Reasons Offers Are Rejected

ReasonHow it happensHow this kit prevents it
Missing mandatory documentChecklist not used; certificate expiredTP-10 with an owner and status per line
Unsigned or unstamped formSigned the PDF, not the pageSignature blocks on every form that needs one
Arithmetic inconsistency between documentsOffer value typed by hand into three placesOne calculated value; TP-14 and TP-09 cross-check to the cent
Unqualified departureDeviation stated in the cover letter onlyTP-12 deviations schedule, cross-referenced from TP-01
Programme inconsistent with the pricePayment ladder written before pricingTP-03 built from the priced BOQ groups
Generic methodologyReused from another tenderTP-02 requires project-specific content per package
Late submissionCourier relied on to meet the deadlineChecklist deadline line, administrative review sign-off

7 What to Change Before You Submit

Mandatory substitutions

Every unit rate in TP-09 is illustrative. It exists to demonstrate the arithmetic of the chain from take-off to offer value, and it is not a market price. Before submission, replace every rate with a live supplier or subcontract quotation, and replace the overhead and profit factors with your own company figures. The quantities may be used as a worked example; the prices may not.

Checklist for adapting the example