Hazards identified for this project, the controls that actually remove them, and who is accountable when the control fails.
Sections7
Critical hazards10
Permits6
Rev.A
Scoring reality: a generic HSE plan copied from another tender scores poorly because the hazards do not match the works. Name the actual high-risk activities on this project — deep excavation, work at height, lifting over live areas — and state the specific control for each.
1 HSE Policy and Responsibilities
No activity on this project is worth an injury. Every person on site has the authority to stop work they
consider unsafe, without needing permission and without recrimination, and the stop-work record is reviewed
by the project manager the same day rather than quietly buried.
Role
HSE responsibility
Accountability
Project Manager
Provides resources, chairs the monthly HSE committee, authorises stop-work
Complies, reports hazards and near misses, uses PPE
Own acts and omissions
Subcontractors
Comply with this plan; their own HSE plan must be equivalent, not inferior
Their own workforce and interfaces
2 Hazard Identification and Risk Assessment (HIRA)
Risk score = likelihood × severity on a 5×5 matrix.
Residual risk is the score after the stated control is in place. Any residual score of 15 or above requires a
written safe system of work approved by the project manager before the activity starts.
#
Activity
Principal hazard
Control measures
Residual
1
Deep excavation
Collapse, engulfment, services strike
Battering or shoring to design; permit to excavate after service scan; edge protection at 1.1 m; ladder access every 7.5 m; no spoil within 1 m of edge
Medium
2
Work at height
Fall from edge or through opening
Guardrails and toe boards to all edges; openings covered and marked; scaffold tagged after inspection; harness and lanyard for MEWP work
Medium
3
Lifting operations
Dropped load, crane overturn, crush
Approved lift plan for tandem or blind lifts; certified operator, banksman and rigger; exclusion zone under the load; no lift over occupied areas without a protected deck
Medium
4
Concrete pours
Chemical burns, pump whip, noise
Gloves and goggles for all cement contact; pump line restrained and inspected; hearing protection within 85 dB; wash facilities on site
Low
5
Electrical work
Electric shock, arc flash
Isolation and lock-out/tag-out; test before touch; no live work without a permit; RCD protection on all temporary supplies
Medium
6
Confined spaces
Asphyxiation, toxic atmosphere
Entry permit; gas test before and during entry; continuous ventilation; attendant at the entry; rescue plan and equipment on standby
High
7
Hot works
Fire
Hot work permit; 10 m clearance of combustibles; fire watch during and 60 min after; extinguisher at the work face
Mechanical aids for loads over 25 kg; team lifts; training in technique
Low
10
Silica & dust
Respiratory disease
Wet cutting or extraction; FFP3 masks; no dry sweeping
Medium
3 Personal Protective Equipment (PPE)
Item
When mandatory
Standard
Safety helmet
At all times on site
EN 397
Safety footwear
At all times on site
EN ISO 20345 S3
High-visibility vest
At all times; Class 3 near plant
EN ISO 20471
Safety glasses
Cutting, grinding, drilling, chemical handling
EN 166
Gloves
Material handling, concrete, steel fixing
EN 388 / EN 374 for chemicals
Hearing protection
Any area above 85 dB(A)
EN 352
Respiratory protection
Dust, silica, solvent vapour
FFP3 / EN 140
Fall arrest harness
MEWP, leading edge, unprotected openings
EN 361 + EN 355 lanyard
4 Permit to Work System
No permit, no work. Permits are issued by the HSE officer for one shift only, are displayed at the work face,
and are closed out by the issuer after inspection — not left to expire unattended.
Permit type
Required for
Issued by
Validity
Excavation
Any excavation deeper than 1.2 m
HSE officer + site engineer
1 shift
Hot work
Welding, cutting, grinding, bitumen
HSE officer
1 shift
Confined space entry
Tanks, pits, manholes, ducts
Project manager + HSE officer
Per entry
Work at height
Above 2 m without permanent protection
HSE officer
1 shift
Lifting / critical lift
Tandem lifts, over live areas, over 80% capacity
Project manager + lift supervisor
Per lift
Electrical isolation
Any work on live or isolated systems
Authorised electrical person
1 shift
5 Training and Awareness
Site induction before first entry, valid for the project, covering site rules, emergency
arrangements, welfare and reporting. No induction, no access — enforced at the gate.
Task-specific training for scaffolding, lifting, confined space, electrical work and plant
operation, with certificates held on file and expiry dates tracked.
Toolbox talks weekly, delivered by the supervisor at the work face, on the hazard of the
week — not a repeat of the induction.
Emergency drills every three months: evacuation, confined-space rescue and first aid response.
6 Emergency Response
Element
Arrangement
Assembly point
Marked, signed, and clear of plant routes; muster checked by roll call and headcount
Emergency contacts
Displayed at the gate, the site office and every floor: ambulance, civil defence, hospital, project manager
First aid
Two trained first aiders per shift; two kits, one at the office and one at the work face
Rescue
Confined-space and height rescue plan with equipment and a trained team on standby during the activity
Fire
Extinguishers at every hot work location and at plant; extinguisher training for all supervisors
Reporting
Any incident, however minor, reported within one hour; serious incidents reported to the authority within the statutory period
7 Incident Reporting and Investigation
Metric
Target
Reported
Lost time injury frequency rate (per million hours)
< 1.0
Monthly
Recordable incidents
Zero
Monthly
Near misses reported
≥ 10 per month (a rising count is a healthy reporting culture)
Monthly
Toolbox talks delivered
100% of planned
Weekly
Open corrective actions older than 30 days
Zero
Weekly
HSE officer
Project manager
Corporate HSE manager
FORM TP-05 · MMC Technical Proposal Kit — English Edition v2.0HSE plan · page 1 of 1