Form TP-06 · Resource Plan

Resource Plan: Organisation, Key Personnel, Equipment and Materials

The evaluator is asking one question: can this bidder actually staff, plant and supply this project? Named people, owned plant and identified sources answer it; general assurances do not.

Sections5
Key staff8
Plant items14
Rev.A
What earns marks: staff named with qualifications and years of experience, plant listed as owned or leased with capacity, and material sources named with an approved-supplier route. A CV that says “civil engineer” without a registration number is a CV nobody can score.

1 Project Organisation Chart

Project DirectorExecutive sponsor · contract authority
Project ManagerDelivery, cost, programme
Contracts ManagerClaims, variations, procurement
Construction ManagerSite production
QA/QC EngineerQuality & records
HSE OfficerSafety & environment
Planning EngineerProgramme & progress
QS / Cost EngineerPayments & variations
MEP CoordinatorServices interfaces
Site EngineersBy zone · 3
ForemenBy trade · 6
SurveyorSetting-out
Document ControlSubmittals
Store KeeperMaterials

2 Key Personnel Schedule

#PositionNameQualificationYears exp.Similar projectsAllocation
1Project Director20%
2Project Manager100%
3Construction Manager100%
4QA/QC Engineer100%
5HSE Officer100%
6Planning Engineer60%
7QS / Cost Engineer50%
8MEP Coordinator80%
9Site Engineer (x3)100%
10Surveyor50%

Allocation is a commitment

A person shown at 100% cannot be shown at 100% on another concurrent project in the same offer. " Evaluators do check this, and a key person double-booked across two tenders is a credibility failure that " taints the whole submission.

3 Abbreviated CVs of Key Personnel

Curriculum Vitae — Key Person 1

ProjectRoleValueYearScope

Repeat this block for each key person, or attach CVs in the same format as an annex and reference them here.

4 Equipment Schedule

#EquipmentCapacity / specQtyOwned / leasedConditionOn site from
1Hydraulic excavator 20 t0.9 m³ bucket2Owned< 5 yrsM1
2Backhoe loaderJCB 3CX class1Owned< 5 yrsM1
3Mobile crane 50 tTelescopic boom1LeasedCertifiedM4
4Tower craneMax 2.5 t @ 50 m1LeasedCertifiedM4
5Concrete pumpTruck-mounted 36 m1LeasedCertifiedM3
6Transit mixer 8 m³With agitator4Leased< 5 yrsM3
7VibratorPoker 50 mm8OwnedGoodM3
8Plate compactor90 kg4OwnedGoodM2
9Generator 250 kVASilenced2OwnedGoodM1
10Water pump 75 mmDiesel6OwnedGoodM2
11ScaffoldingCuplock, 3,000 m²1 setOwnedCertifiedM5
12MEWP 16 mArticulated boom1LeasedCertifiedM6
13Survey total station2 second accuracy2OwnedCalibratedM1
14Laser levelSelf-levelling4OwnedCalibratedM1

5 Material Sources

MaterialSource / supplierLocationApproval routeLead time
Ready-mix concreteBatching plantMix design + trial mix3 days
Reinforcement steelMill / stockistMill certificates + sample14 days
CementDistributorCertificate of conformity7 days
BlockworkLocal factorySample + test certificate10 days
Structural steelFabricatorShop drawings + mill certs30 days
WaterproofingApproved applicatorManufacturer warranty10 days
Tiles & sanitarywareImporterSample board30 days
Electrical cable & boardsDistributorType test certificates21 days
HVAC equipmentManufacturerPerformance data + sample45 days
Fire protectionApproved supplierCivil defence listing30 days
Planning engineer
Project manager
General manager