Resource Plan: Organisation, Key Personnel, Equipment and Materials
The evaluator is asking one question: can this bidder actually staff, plant and supply this project? Named people, owned plant and identified sources answer it; general assurances do not.
Sections5
Key staff8
Plant items14
Rev.A
What earns marks: staff named with qualifications and years of experience, plant listed as owned or leased with capacity, and material sources named with an approved-supplier route. A CV that says “civil engineer” without a registration number is a CV nobody can score.
A person shown at 100% cannot be shown at 100% on another concurrent project in the same offer. "
Evaluators do check this, and a key person double-booked across two tenders is a credibility failure that "
taints the whole submission.
3 Abbreviated CVs of Key Personnel
Curriculum Vitae — Key Person 1
Project
Role
Value
Year
Scope
Repeat this block for each key person, or attach CVs in the same format as an annex and reference them here.
4 Equipment Schedule
#
Equipment
Capacity / spec
Qty
Owned / leased
Condition
On site from
1
Hydraulic excavator 20 t
0.9 m³ bucket
2
Owned
< 5 yrs
M1
2
Backhoe loader
JCB 3CX class
1
Owned
< 5 yrs
M1
3
Mobile crane 50 t
Telescopic boom
1
Leased
Certified
M4
4
Tower crane
Max 2.5 t @ 50 m
1
Leased
Certified
M4
5
Concrete pump
Truck-mounted 36 m
1
Leased
Certified
M3
6
Transit mixer 8 m³
With agitator
4
Leased
< 5 yrs
M3
7
Vibrator
Poker 50 mm
8
Owned
Good
M3
8
Plate compactor
90 kg
4
Owned
Good
M2
9
Generator 250 kVA
Silenced
2
Owned
Good
M1
10
Water pump 75 mm
Diesel
6
Owned
Good
M2
11
Scaffolding
Cuplock, 3,000 m²
1 set
Owned
Certified
M5
12
MEWP 16 m
Articulated boom
1
Leased
Certified
M6
13
Survey total station
2 second accuracy
2
Owned
Calibrated
M1
14
Laser level
Self-levelling
4
Owned
Calibrated
M1
5 Material Sources
Material
Source / supplier
Location
Approval route
Lead time
Ready-mix concrete
Batching plant
Mix design + trial mix
3 days
Reinforcement steel
Mill / stockist
Mill certificates + sample
14 days
Cement
Distributor
Certificate of conformity
7 days
Blockwork
Local factory
Sample + test certificate
10 days
Structural steel
Fabricator
Shop drawings + mill certs
30 days
Waterproofing
Approved applicator
Manufacturer warranty
10 days
Tiles & sanitaryware
Importer
Sample board
30 days
Electrical cable & boards
Distributor
Type test certificates
21 days
HVAC equipment
Manufacturer
Performance data + sample
45 days
Fire protection
Approved supplier
Civil defence listing
30 days
Planning engineer
Project manager
General manager
FORM TP-06 · MMC Technical Proposal Kit — English Edition v2.0TP-KIT v2.0 · English Edition