Form TP-08 · Risk Register & Mitigation Plan

Risk Analysis and Mitigation Plan

Risks the bidder has actually priced and planned for. A register that lists only force majeure tells the evaluator the bidder has not thought about this project.

Sections4
Risks14
Matrix5×5
Rev.A
Scoring logic: each risk needs an owner, a trigger that tells you it is happening, a mitigation that acts before the impact, and a contingency with a value and a time allowance. “Monitor closely” is not a mitigation.

1 Risk Assessment Methodology

Risk score = likelihood × consequence, each scored 1–5. Scores are reviewed at the weekly progress meeting and any movement of two points or more is reported to the project director.

1 Insign.2 Minor3 Moderate4 Major5 Severe
5 Almost certain510152025
4 Likely48121620
3 Possible3691215
2 Unlikely246810
1 Rare12345
BandScoreRequired response
Critical15–25Project director decision; written plan before activity starts
High10–14Project manager plan; weekly review
Medium5–9Construction manager plan; monthly review
Low1–4Accepted; monitored through routine reporting

2 Risk Register

#Risk eventCategoryLCScoreMitigation (before impact)Trigger to actOwner
1Late site handover / possession delayClient3412Mobilisation plan with a 30-day compressed start; advance procurement of long-lead items against a letter of intentHandover date missed by 7 daysPM
2Ground conditions differ from the soil reportTechnical3412Pre-bid site visit and local knowledge; provisional allowance for rock excavation; early trial pitRefusal rates in the first excavation panelCM
3Utility diversion delays excavationExternal3412Service scan and trial trenches before excavation permit; diversion application in month 1Uncharted service foundCM
4Design coordination gaps between disciplinesDesign4312Coordinated services model before first fix; weekly clash report with owners and dates>5 open clashes older than 14 daysMEP Coord.
5Late approval of materials or shop drawingsClient4312Submittal register issued in week 1 with dates back-planned from the programme; escalate at day 10Any submittal unreturned at 10 daysQA/QC
6Long-lead equipment delivery slipSupply3412Order at award; factory acceptance test scheduled; alternative approved source identifiedDelivery forecast slips 2 weeksProcurement
7Cash flow gap on interim paymentsFinancial3412Payment application submitted on the contract date with full substantiation; retention and bond costs in the cash curveCertification delayed beyond 21 daysContracts
8Price escalation on steel and cementMarket339Firm quotations for the first 6 months; escalation clause position stated in the offerIndex movement >5%QS
9Adverse weather stopping external worksExternal339Weather days in the programme; sequence external works in the dry window3 consecutive lost daysPlanner
10Labour shortage for a specialist tradeResource339Framework subcontractors with capacity commitments; second source identified per package<80% of planned labour on siteCM
11Safety incident causing a stop-work orderHSE2510HSE plan with hold-point permits; daily inspection; stop-work authority for every workerAny lost-time incidentHSE
12Non-conformance requiring demolition and rebuildQuality248ITP hold points; no pour without signed inspection; mock-up approval before finishesAny NCR rated majorQA/QC
13Scope creep through undocumented instructionsContract428Written instruction required before work; daily site diary; variation registerAny verbal instruction receivedContracts
14Handover delay from incomplete O&M and as-builtsCloseout339Closeout register opened at 50% completion, not at the end; documents tracked as line itemsAny closeout item open at 85% progressQA/QC

3 Critical Risks and Contingency

Critical riskContingency (time)Contingency (cost)Trigger for release
Ground conditions
Utility diversion
Long-lead equipment
Payment delay

4 Risk Management During Execution

Project manager
Risk / contracts manager