| 1 | Late site handover / possession delay | Client | 3 | 4 | 12 | Mobilisation plan with a 30-day compressed start; advance procurement of long-lead items against a letter of intent | Handover date missed by 7 days | PM |
| 2 | Ground conditions differ from the soil report | Technical | 3 | 4 | 12 | Pre-bid site visit and local knowledge; provisional allowance for rock excavation; early trial pit | Refusal rates in the first excavation panel | CM |
| 3 | Utility diversion delays excavation | External | 3 | 4 | 12 | Service scan and trial trenches before excavation permit; diversion application in month 1 | Uncharted service found | CM |
| 4 | Design coordination gaps between disciplines | Design | 4 | 3 | 12 | Coordinated services model before first fix; weekly clash report with owners and dates | >5 open clashes older than 14 days | MEP Coord. |
| 5 | Late approval of materials or shop drawings | Client | 4 | 3 | 12 | Submittal register issued in week 1 with dates back-planned from the programme; escalate at day 10 | Any submittal unreturned at 10 days | QA/QC |
| 6 | Long-lead equipment delivery slip | Supply | 3 | 4 | 12 | Order at award; factory acceptance test scheduled; alternative approved source identified | Delivery forecast slips 2 weeks | Procurement |
| 7 | Cash flow gap on interim payments | Financial | 3 | 4 | 12 | Payment application submitted on the contract date with full substantiation; retention and bond costs in the cash curve | Certification delayed beyond 21 days | Contracts |
| 8 | Price escalation on steel and cement | Market | 3 | 3 | 9 | Firm quotations for the first 6 months; escalation clause position stated in the offer | Index movement >5% | QS |
| 9 | Adverse weather stopping external works | External | 3 | 3 | 9 | Weather days in the programme; sequence external works in the dry window | 3 consecutive lost days | Planner |
| 10 | Labour shortage for a specialist trade | Resource | 3 | 3 | 9 | Framework subcontractors with capacity commitments; second source identified per package | <80% of planned labour on site | CM |
| 11 | Safety incident causing a stop-work order | HSE | 2 | 5 | 10 | HSE plan with hold-point permits; daily inspection; stop-work authority for every worker | Any lost-time incident | HSE |
| 12 | Non-conformance requiring demolition and rebuild | Quality | 2 | 4 | 8 | ITP hold points; no pour without signed inspection; mock-up approval before finishes | Any NCR rated major | QA/QC |
| 13 | Scope creep through undocumented instructions | Contract | 4 | 2 | 8 | Written instruction required before work; daily site diary; variation register | Any verbal instruction received | Contracts |
| 14 | Handover delay from incomplete O&M and as-builts | Closeout | 3 | 3 | 9 | Closeout register opened at 50% completion, not at the end; documents tracked as line items | Any closeout item open at 85% progress | QA/QC |